The Sprint planning and retrospective meeting for the Whitebox project focused on addressing several critical issues impacting integration testing and project timelines. Avinash and Miloš discussed problems with integration tests running in containers, expressing frustration over slow CI processes and the importance of proper time logging. The team outlined the need to prioritize efficiency and set a firm September deadline for the V1 release, while reviewing technical challenges related to mobile support and project architecture. During the current sprint review, the team assessed various tickets, determining action items to unblock progress and improve collaboration as Xavier prepares for an extended absence. Action items were assigned, including creating a V1 planning document, forking the Poetry package manager to resolve ongoing issues, and updating ticket scopes, with a focus on meeting the September deadline and ensuring a smooth workflow during transitions.
|