Project behind schedule: Xavier reports a 40% delay, requiring an additional 6-8 sprints to meet deadlines.
Current POC status shows functional camera feeds and flight interface, but lacks critical playback features and full functionality.
Video recording capabilities demonstrated, with low-definition streaming at 40-60MB/min and HD at 0.5GB/min; however, HD processing is currently impractical.
Hardware limitations identified: Raspberry Pi needs dual wireless interface for camera connection, causing driver conflicts.
Device connectivity issues due to USB adapter compatibility problems; alternative SBCs with M.2 support being considered.
Avinash reports severe burnout compounded by city flooding, requesting a break amidst deadline pressure.
Significant work hour reduction noted across the team, with logs showing weeks of inactivity due to low motivation.
Key tasks for the next sprint include creating a demo video, a root cause analysis document, and updating the project timeline.
Frontend completion estimated to take 4 sprints, focusing on playback implementation and comments system functionality.
Definition of done for POC needs clarification, considering anonymous user access and optional settings manager.